RUSA 2.0:
Rashtriya Uchchatar Shiksha Abhiyan (RUSA) is a centrally sponsored programme, launched in 2013 with an aim to provide strategic funding to eligible higher education institutes in states. To improve access, equity and quality in higher education through planned development of higher education are the key objectives of RUSA. There are total of fourteen (14) different components under which the funds are disbursed.
Chakdaha College was selected for RUSA 2.0 funding in 2018 under Component 9: “Infrastructure Grants to Colleges” and Component-11: “Equity Initiatives”.
The College has a Project Monitoring Unit known as RUSA-PMU to supervise all the works as described in DPR. The Project Monitoring Unit (PMU) was formed as per notification no. 159-EH/RUSA-223/18 dated 16.07.18, published by the Directorate of Rashtriya Uchchatara Shiksha Abhiyan (RUSA), Department of Higher Education, Science & Technology and Biotechnology, Govt. of West Bengal. The composition of the RUSA-PMU of Chakdaha College is as follows:
SL. | Name | Designation |
---|---|---|
1 | Principal/Teacher-in-Charge | Chairperson |
2 | Dr. Saikat Sarkar, Associate Professor in Chemistry | Coordinator |
3 | Dr. Arun Kumar Nandi, Associate Professor in Economics & IQAC Coordinator | Member |
4 | Dr. Paritosh Biswas, Associate Professor in Chemistry | Member |
5 | Dr. Nikhil Kumar Mandal, Associate Professor in Economics | Member |
6 | Dr. Sabina Jesmin, Assistant Professor in Philosophy | Member |
7 | Dr. Sahanous Mallick, Assistant Professor in Mathematics & Bursar | Member |
8 | Dr. Iftikar Alam, Assistant Professor in Geography | Member |
9 | Dr. Ranjan Karmakar, Librarian | Member |
Details of Component-9:
Total fund approved: Rs. 2.0 Cr
Total fund received by the College till date: Rs. 1.0 Cr (1st installment) [Order No. 173-EH/RUSA-240/18/Comp-9, dated 01.08.2018]
Works Done under Component-9:
SL. | Project Name | Project Description | Project Expenditure Incurred | Project Status |
---|---|---|---|---|
1 | New Construction | Construction of (a) one staff canteen building with three storied foundation and (b) three additional rooms at 2nd Floor over existing building and two toilets for Boys and Girls | Rs. 0.4981595 Cr | 95 % Completed |
2 | Renovation | Up-gradation and Renovation of (a) Two floors of Boys' Hostel (b) Academic Building (c) Administrative Building (d) Library Building | Rs. 0.1670518 Cr | Main work completed |
3 | Procurement | Purchase for up-gradation of (a) Laboratory equipments (b) Laptop and Printers (c) Books (d) Gymnasium and sports equipments/items | Rs. 0.2484210 Cr | Procurement under 1st Phase installment completed |
Details of Component-11:
Total fund approved: Rs. 0. 8944694 Cr
Total fund received by the College till date: Rs. 0.4472347 Cr (1st installment) [Order No. 343-EH/RUSA-01/19/Comp-11, dated 26.11.2019]
Works Done under Component-11:
SL. | Project Name | Project Description | Project Expenditure Incurred | Project Status |
---|---|---|---|---|
1 | New Construction | Construction of Girls’ Hostel | Rs. 104040.00 (only for soil testing) | Paper submitted to the P.W.Dte., Social Sector, Krishnagar, Nadia for taking up and completing the Project |